Fincon - Five workers - Kenyon, Gilberto, Jose, Oscar, Eddie Fincon stripped all remaining laser forms from the first slab pour and cut the remaining concrete that needed to be cut. Fincon added laser forms so that all forms are added other than enough space for the screed to get inside for the pour. The ground was evened out around the plumbing and all over the floor so that it is as level and flat as possible. Blankets were placed over the rebar where the slab will be poured to help with frost protection on the ground. High Fly Rebar - High Fly Rebar added all of the rebar for the slab.