Fincon — Three workers — Kenyon, Chino, Isai— 1:00-5:00 Interior spot footings were stripped and concrete blankets were replaced on top of the footings. The conex was cleaned and organized.
0 Comments
Fincon — Seven workers — Kenyon, Cory, Larry, Diego, Jose, Alexander, Anjel — 7:00-6:00 Seven FS8.5 interior spot footings were poured. Bolt patterns were centered and put into the concrete. Dirt pile was moved for the future placement of a conex. The footings were covered with concrete blankets so that the concrete will not freeze. Gravel track pad placed in front of the conex so that dirt will not be carried inside of it. Schoonover Plumbing — Two workers — Pipes were filled in using Fincon's skid-steer. Fincon — Five workers — Kenyon, Diego, Jose, Alexander, Angel -- 8:00-5:00 Visqueen and string added to seven FS8.5 interior spot footing in preparation for the concrete on Friday. The rebar and rebar chairs were also added to each of the seven FS8.5 interior spot footings. The four center points of each interior spot footing were marked with a nail using the total station. The skid-steer was used to clear a path and even out the ground for the delivery of the conex that day. Schoonover Plumbing — Two workers — Excavation and layout of pipes. Fincon — Two workers — Cory, Kenyon — Topcon total station used to match the existing points laid out by the surveyor and to create two control points. Interior spot footings were also graded to the proper height. -- 9:00-5:00 Dyer Excavation -- Gravel path on the northeast end of the job site worked on. Schoonover Plumbing — Two workers — Excavation and layout of pipes. Fincon — Gravel was added to interior spot footings so that they were at the proper grade. A Caterpillar skid-steer was dropped off at the job site. Organization and clean up of job site for future placement of trailers. -- 8:00-4:00 Dyer Excavation -- Two silt fences added to the west end of the job site to meet Springville City regulations. Gravel path added to the northeast end of the site for entry and exit of job site. Schoonover Plumbing — Two workers — Excavation and layout of pipes. Fincon — Three workers — Kenyon, Chino, Isai
- 9:00-4:00 Seven FS8.5 interior spot footings were formed. The fork lift was worked on and three trash cans were installed and the job was cleaned up. Schoonover Plumbing — Two workers — Excavation and layout of pipes. High of 52 degrees, low of 30 degrees. Interior spot footings were dug by Dyer Excavation. Interior spot footings ready to be formed by Fincon. Plumbing on schedule to start.
|
AuthorKenyon Finch Archives
April 2020
Categories |