Fincon — Seven workers — Kenyon, Cory, Larry, Diego, Jose, Alexander, Anjel — 7:00-6:00 Seven FS8.5 interior spot footings were poured. Bolt patterns were centered and put into the concrete. Dirt pile was moved for the future placement of a conex. The footings were covered with concrete blankets so that the concrete will not freeze. Gravel track pad placed in front of the conex so that dirt will not be carried inside of it. Schoonover Plumbing — Two workers — Pipes were filled in using Fincon's skid-steer.