Fincon - Panels 10 -24 have been laid out and formed under the direction of Fincon. These panels will be poured at a later date. Various materials arrived at the job such as weld plates. High Fly Rebar - High Fly tied rebar that will be placed in the panels.
0 Comments
Fincon - 5 workers - Kenyon, Cory, Eddie, Grandpa, FilimoneTemporary power was added to the job site and connected to the office trailer. All of the blankets were removed from the pour of the second half of the slab.
Fincon - 13 workers - Kenyon, Gilberto, Noel, Ricardo, Izzy, Chino, Fernando, Big Al, Armando, Oscar, Luis, Cory, Larry. Fincon poured and finished the second section of the floor of the building. 310 yards of concrete were provided by Jack B. Parson's Company and Dudley Concrete Pumping pumped the concrete. Fincon used power trowels to finish the concrete. Fincon then snapped lines for the lines and saw cut the concrete. Joint savers were placed in the cuts to avoid cracking where the cuts meet. Concrete blankets were placed over the concrete to avoid damage to the concrete from freezing. JJ Laser Screed - JJ Laser Screed screeded the concrete at 6 inches. Fincon - The blankets were lifted up and snow was removed from where the slab will be. After the snow was removed, blankets were replaced over the rebar where the slab will be poured to help with frost protection on the ground. |
AuthorKenyon Finch Archives
April 2020
Categories |