Spring Pointe Job

Rebar installed, concrete cut, laser forms added, laser forms stripped

12/31/2019

0 Comments

 
Fincon - Five workers - Kenyon, Gilberto, Jose, Oscar, Eddie  Fincon stripped all remaining laser forms from the first slab pour and cut the remaining concrete that needed to be cut.

Fincon added laser forms so that all forms are added other than enough space for the screed to get inside for the pour.

The ground was evened out around the plumbing and all over the floor so that it is as level and flat as possible.

Blankets were placed over the rebar where the slab will be poured to help with frost protection on the ground.

High Fly Rebar - High Fly Rebar added all of the rebar for the slab.

0 Comments

Blankets removed from slab and laser forms stripped

12/24/2019

0 Comments

 
Fincon - Four workers - Oscar, Jose, Eddie, Ricardo - Fincon removed the blankets from the slab and stripped the laser forms.
0 Comments

First section of the floor poured

12/20/2019

0 Comments

 
Fincon - Nine workers for the pour - Chino, Izzy, Noel, Diego, Alexander, Jose, Ricardo, Kenyon, Cory  

11 workers for cutting the concrete - Chino, Izzy, Noel, Fernando, Diego, Alexander, Luis, Jose, Armando, Ricardo, Kenyon

Fincon poured and finished the first section of the floor of the building. 350 yards of concrete were provided by Jack B. Parson's Company and Dudley Concrete Pumping pumped the concrete.

Fincon used power trowels to finish the concrete. Fincon then snapped lines for the lines and saw cut the concrete. Joint savers were placed in the cuts to avoid cracking where the cuts meet. 

Concrete blankets were placed over the concrete to avoid the damage to the concrete from freezing.

JJ Laser Screed - JJ Laser Screed screeded the concrete at 6 inches.


0 Comments

Rebar set and tied for first pour

12/18/2019

0 Comments

 
High Fly Rebar - High Fly Rebar set and tied the rebar in the laser forms one foot on center. Rebar was set and ready for the first 350 cubic yards of concrete to be poured on Friday.

Dyer Excavation - Dyer Excavation worked on building a second entrance to the project and added a large washout for the concrete trucks and pump.
0 Comments

Styrofoam blockouts added

12/17/2019

0 Comments

 
Fincon - Styrofoam blockouts were added to each of the footings.
0 Comments

Laser forms added

12/16/2019

0 Comments

 
Fincon put in four inch high laser forms around the project to prepare for the rebar so that the six inch floor can be poured.
0 Comments

FS12 spot footings filled and compacted

12/11/2019

0 Comments

 
Fincon - Two workers - Chino, Noel

Fincon stripped the FS12 spot footings. 

Dyer Excavation filled and compacted the FS12 spot footings.
0 Comments

Final spot footings poured

12/10/2019

0 Comments

 
The two FS12 spot footings were inspected and poured by Fincon. Dudley Concrete Pumping pumped the concrete while Jack B. Parson provided the concrete. 

​
0 Comments

Two final spot footings formed

12/9/2019

0 Comments

 
The two final spot footings were formed by Fincon. Rebar was placed by High Fly Rebar. Fincon added the bolt templates,  anchor bolts, and pencil rods.

Dyer Excavation filled and compacted the other spot footings.


0 Comments

    Author

    Kenyon Finch

    As Builds
    City Inspections
    Special Inspections
    Concrete Log

    Archives

    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019

    Categories

    All

    RSS Feed

Proudly powered by Weebly
  • Home
  • Current Projects
  • Completed Projects
  • About US
  • Apply for a Job
  • Contact