Spring Pointe Job

Total Station used to create Control Points

11/20/2019

0 Comments

 
Fincon  —  Two workers  — Cory, Kenyon — Topcon total station used to match the existing points laid out by the surveyor and to create two control points. Interior spot footings were also graded to the proper height.  


-- 9:00-5:00


Dyer Excavation -- Gravel path on the northeast end of the job site worked on.


Schoonover Plumbing  — Two workers  — Excavation and layout of pipes.