Fincon — Five workers — Kenyon, Diego, Jose, Alexander, Angel -- 8:00-5:00 Visqueen and string added to seven FS8.5 interior spot footing in preparation for the concrete on Friday. The rebar and rebar chairs were also added to each of the seven FS8.5 interior spot footings. The four center points of each interior spot footing were marked with a nail using the total station. The skid-steer was used to clear a path and even out the ground for the delivery of the conex that day. Schoonover Plumbing — Two workers — Excavation and layout of pipes.