All panels erected, grout poured, joist and deck started

4/13/2020

0 Comments

 
Fincon - Fincon finished erecting all of the panels of the building. Fincon secured all panels with braces and poured the grout around the building.

Wasatch Steel Erectors- Wasatch Steel Erectors began placing, fastening and securing the joist and deck.